Infernillo HPP
The Contract for hydro generators modernization of hydro units number 5 and number 6 of Infernillo HPP (Mexico) with the nominal capacity increase of each hydro generator from 180 MVA to 211 MVA.
The scope of EMECO activities includes the hydro generators parameters choice analysis, design, technical documentation development and supply of two sets of the stator, stator core segments, as well as installation tools set.
Equipment delivery time: the first set - December 2007, a second set - September 2008.
The Customer is the Federal Electricity Commission of Mexico (CFE) - one of the world's largest electricity producers and suppliers.